21 TEPNG projects (2010–2014) plus our own showcase builds — every photograph on this page is real site work.
OML 102 corroded spools replacement.
Yellow-coated spools, elbows and manifolds fabricated in our Port Harcourt yard and installed offshore under PO 4960067151. Hydrotested, NDT-cleared and delivered 100% complete.
- ASME B31.3 compliant fabrication
- Yard fabrication, offshore installation
- Full hydrotest and NDT records
- 21 TEPNG projects — all 100%
Some completed projects.
Fabrication, structural, marine and plant work — H&D crews and H&D photographs.
OML 102 spools in the yard
Piping
Spool erection offshore
Piping
OWT structural installation (via PMNL)
Structural
Mezzanine deck, WHCP & SDV panels
Structural
Notore jetty with Groudtech
Marine
Reclamation and swamp piling
Marine
Workshop structural installation — Unilever
Industrial
Plant arena project — Nigerian Breweries
Industrial
HVAC upgrade project
Industrial
TEPNG projects (21 records).
Purchase order, scope and completion status straight from our project register. Every listed scope closed at 100%.
| S/N | PO / Contract | Project title | Date | Status |
|---|---|---|---|---|
| 1 | 4560066701 |
OML 102, OFP1 Repair & Change-out of Crane Boom (Critical) | 11-Dec-10 | 100% |
| 2 | 4560074654 |
OML 58, OB 118 Pre-rig Arrival Works | 11-Jun-10 | 100% |
| 3 | 4560070344 |
OML 99, AMD2 HP/LP/MP Manifold Extension | 17-Nov-11 | 100% |
| 4 | 4560070369 |
OML 102, Ofon Piping Revamp Phase 1 | 08-Sep-11 | 100% |
| 5 | 4560082180 |
OML 102, Ofon Piping Revamp Phase 2 | 08-Oct-12 | 100% |
| 6 | 4260020376 |
OML 100, FSO OWT-TANK 8C Works | 13-Jul-12 | 100% |
| 7 | Pending — add PO |
Client to confirm (row 7 of H&D track record) | — | 100% |
| 8 | Pending — add PO |
Client to confirm (row 8 of H&D track record) | — | 100% |
| 9 | Pending — add PO |
Client to confirm (row 9 of H&D track record) | — | 100% |
| 10 | Pending — add PO |
Client to confirm (row 10 of H&D track record) | — | 100% |
| 11 | Pending — add PO |
Client to confirm (row 11 of H&D track record) | — | 100% |
| 12 | 4960067151 |
OML 102 — Ofon 33 Flowline Replacement OFD1 | 05-Feb-13 | 100% |
| 13 | Pending — add PO |
Client to confirm (row 13 of H&D track record) | — | 100% |
| 14 | Pending — add PO |
Client to confirm (row 14 of H&D track record) | — | 100% |
| 15 | Pending — add PO |
Client to confirm (row 15 of H&D track record) | — | 100% |
| 16 | Pending — add PO |
Client to confirm (row 16 of H&D track record) | — | 100% |
| 17 | Pending — add PO |
Client to confirm (row 17 of H&D track record) | — | 100% |
| 18 | Pending — add PO |
Client to confirm (row 18 of H&D track record) | — | 100% |
| 19 | Pending — add PO |
Client to confirm (row 19 of H&D track record) | — | 100% |
| 20 | Pending — add PO |
Client to confirm (row 20 of H&D track record) | — | 100% |
| 21 | 4560102849 |
OWT Rotation of Polishing Unit | 12-Aug-14 | 100% |
Rows marked “pending — add PO” are being completed by the client from their register; the table is editable in the Elementor text editor or via the theme shortcode.
Your scope could be the next line in this table.
Fabrication, turnaround maintenance, structural, marine or as-built — send the scope and we will price it properly.